PROCESS

Process

  • 01

    Raw Material

  • 02

    Cutting

  • 03

    Heating

  • 04

    Forging

  • 05

    Normalizing Heat Treatment

  • 06

    Machining

  • 07

    QT Heat Treatment

  • 08

    Inspection(UT,MT)

Lead time may vary depending on product delivery conditions as shown below.

  • Delivery in forged condition (Normalizing): at least 7 to 10 days
  • Rough processing delivery (if no quenching tempering): at least 10 to 15 days
  • Rough processing delivery (if quenching tempering is included): At least 15 to 20 days
* If there are other special processes, the lead time can be adjusted by prior agreement.